East Tower
Floor 09 : Slab 50% completed
Floor 08 : Slab completed 21st November 07
Floor 07 : Slab completed 12th November 07
West Tower
Floor 08 : Slab 25% completed
Floor 07 : Slab completed 23rd November 07
Floor 06 : Slab completed 13th November 07
Sunday 2 December 2007
Subscribe to:
Posts (Atom)