Sunday 19 August 2007

01 August 07 - 19 August 07

Until 25th August almost all workers are concentrating on completing the huge Transfer Beams on the 1st Floor.

Once Transfer Beams are completed ; vertical progress of the towers can recommence.

A small number of workers have been allocated to finish the swimming pool structure also by 25th August.

Maximum number of workers at site = 410

Monday 6 August 2007

Progress 30th June to 31st July 07


Panoramic view from S.E Corner 31st July 07



Panoramic view from S.E Corner 30th June 07