Monday 11 August 2008

Topping Out Ceremony : 14th July 2008


Left to Right

Mr. Song Zu Qiang - Vice Project Manager - BUCG
Mr. Albert Chan - Tung Shing Group
Mr. Zadig Chan - Chairman - Tung Shing Group
Mr. Tu Chun Hong - Construction Manager - BUCG
Mr. Lee Wing Chew - Tung Shing Group
Mr. Ronald Nam Kwok Fu - Managing Director - Tung Shing Group
Mr. Andrew Shipley - Project Manager - AIC Management
Mr. Malcolm Whitehouse - General Director - Leonidas Management
Mr. Gary McKinnon - General Director - AIC Management
Mr. Ghuri Wai Yip Wong - Deputy General Director - Tung Shing Group


Progress Update : 30th June 2008


Structural Works Completed 30th June 2008
  • Start date (Basement 02 Slab) : 27th April 07
  • Finish date (Roof Slab) : 30th June 08
  • Time for Completion : 430 days (14.14 months)
  • Average number of structural floors per month : 2.05 (Basement 02 to Roof = 29 structural slabs)
  • Total number of concrete pours : 940 No.
  • Average number of concrete pours per day : 2.19 No.

Monday 5 May 2008

Progress Update : 30th April 2008



(View From East Tower Floor 22 - Looking West)

West Tower
Floor 23 slab completed : 29th April 08
Floor 22 slab completed : 17th April 08
Floor 21 slab completed : 8th April 08










(View From East Tower Floor 22 - Looking East)

East Tower
Floor 21 slab completed : 27th April 08
Floor 20 slab completed : 14th April 08
Floor 19 slab completed : 2nd April 08

Progress Update : 31st March 2008


West Tower
Floor 21 slab completed : 50%
Floor 20 slab completed : 22nd March 08
Floor 19 slab completed : 12th March 08
Floor 18 slab completed : 4th March 08













East Tower
Floor 19 slab completed : 50%
Floor 18 slab completed : 12th March 08

Tuesday 18 March 2008

Progress Update : 29th February 2008


East & West Towers

Floor 18 slab : Under construction
Floor 17 slab completed : 28th Jan 08
Floor 16 slab completed : 1st Feb 08

(Progress in Feb affected by Lunar New (Tet) Year Holidays)

Progress Update : 31st January 2008

East & West Towers

Floor 16 slab : under construction
Floor 15 slab completed : 24th Jan 08
Floor 13 slab completed : 14th Jan 08
Floor 12 slab completed : 06th Jan 08

Wednesday 2 January 2008

Progress Update : 31st December 2007



View across West lake from West Tower Floor 12





West Tower

Floor 12 slab : under construction
Floor 11 slab completed : 30th Dec 07
Floor 10 slab completed : 22nd Dec 07
Floor 09 slab completed : 13th Dec 07
Floor 08 slab completed : 3rd Dec 07










East Tower

Floor 13 slab : under construction
Floor 12 slab completed : 31st Dec 07
Floor 11 slab completed : 22nd Dec 07
Floor 10 slab completed : 13th Dec 07
Floor 09 slab completed : 3rd Dec 07

Sunday 2 December 2007

Progress Update : 30th November 2007

East Tower

Floor 09 : Slab 50% completed
Floor 08 : Slab completed 21st November 07
Floor 07 : Slab completed 12th November 07














West Tower


Floor 08 : Slab 25% completed
Floor 07 : Slab completed 23rd November 07
Floor 06 : Slab completed 13th November 07

Sunday 4 November 2007

Progress Update : 05 November 07

East Tower :
Floor 07 : Under Construction
Floor 06 : Slab completed 01 November 07
Floor 05 : Slab completed 21 October 07
Floor 04 : Not used
Floor 03 : Slab completed 02 October 07
View across West Lake from East Tower Floor 07





West Tower :
Floor 06 : Under construction
Floor 05 : Slab completed 02 November 07
Floor 04 : Not used
Floor 03 : Slab completed 20 October 07


View across West Lake from West Tower Floor 06







Panoramic view looking South : End October 07







Panoramic view looking South : End September 07

Sunday 23 September 2007

Floor 01 & Floor 02 : Structure : Completed


Floor 02 Structure was completed on 20th Sept 07

Swimming Pool Structure was completed on 16th Sept 07

Floor 01 Structure (including Transfer Beams ) was completed on 27th August 07