Monday 11 August 2008

Progress Update : 30th June 2008


Structural Works Completed 30th June 2008
  • Start date (Basement 02 Slab) : 27th April 07
  • Finish date (Roof Slab) : 30th June 08
  • Time for Completion : 430 days (14.14 months)
  • Average number of structural floors per month : 2.05 (Basement 02 to Roof = 29 structural slabs)
  • Total number of concrete pours : 940 No.
  • Average number of concrete pours per day : 2.19 No.