Progress Update : 30th April 2008



(View From East Tower Floor 22 - Looking West)

West Tower
Floor 23 slab completed : 29th April 08
Floor 22 slab completed : 17th April 08
Floor 21 slab completed : 8th April 08










(View From East Tower Floor 22 - Looking East)

East Tower
Floor 21 slab completed : 27th April 08
Floor 20 slab completed : 14th April 08
Floor 19 slab completed : 2nd April 08

Progress Update : 31st March 2008


West Tower
Floor 21 slab completed : 50%
Floor 20 slab completed : 22nd March 08
Floor 19 slab completed : 12th March 08
Floor 18 slab completed : 4th March 08













East Tower
Floor 19 slab completed : 50%
Floor 18 slab completed : 12th March 08