Sunday 2 December 2007

Progress Update : 30th November 2007

East Tower

Floor 09 : Slab 50% completed
Floor 08 : Slab completed 21st November 07
Floor 07 : Slab completed 12th November 07














West Tower


Floor 08 : Slab 25% completed
Floor 07 : Slab completed 23rd November 07
Floor 06 : Slab completed 13th November 07

Sunday 4 November 2007

Progress Update : 05 November 07

East Tower :
Floor 07 : Under Construction
Floor 06 : Slab completed 01 November 07
Floor 05 : Slab completed 21 October 07
Floor 04 : Not used
Floor 03 : Slab completed 02 October 07
View across West Lake from East Tower Floor 07





West Tower :
Floor 06 : Under construction
Floor 05 : Slab completed 02 November 07
Floor 04 : Not used
Floor 03 : Slab completed 20 October 07


View across West Lake from West Tower Floor 06







Panoramic view looking South : End October 07







Panoramic view looking South : End September 07

Sunday 23 September 2007

Floor 01 & Floor 02 : Structure : Completed


Floor 02 Structure was completed on 20th Sept 07

Swimming Pool Structure was completed on 16th Sept 07

Floor 01 Structure (including Transfer Beams ) was completed on 27th August 07

Sunday 19 August 2007

01 August 07 - 19 August 07

Until 25th August almost all workers are concentrating on completing the huge Transfer Beams on the 1st Floor.

Once Transfer Beams are completed ; vertical progress of the towers can recommence.

A small number of workers have been allocated to finish the swimming pool structure also by 25th August.

Maximum number of workers at site = 410

Monday 6 August 2007

Progress 30th June to 31st July 07


Panoramic view from S.E Corner 31st July 07



Panoramic view from S.E Corner 30th June 07

Friday 27 July 2007

22nd July 07 to 27 July 07

Binh (AIC) , Huong (AIC) , Tuan (AIC), Huong (AIC)

27 July 07 : Mezzanine Floor : Sections E2 and E4 : Core Wall : Stairs

26 July 07 : Mezzanine Floor : Section W2 : Core Wall : Stairs

22 July 07 : Mezzanine Floor Slab : Section 6

22 July 07 : Mezzanine Floor Slab : Section 5

17th July 2007 to 21 July 2007

Wang Lin (BUCG) & Yang Shuli (BUCG)

21 July 07 : Mezzanine Floor Slab : Section 4

21 July 07 : Mezzanine Floor Slab : Section 3

17 July 07 : Mezzanine Floor : Section 1 : 6 No. Columns

17 July 07 : Mezzanine Floor Slab : Section 2

17 July 07 : Ground Floor Slab : Section 8 : Part 4 of 4

17 July 07 : Ground Floor Slab : Section 8 : Part 3 of 4

Tuesday 17 July 2007

10th July 07 to 16th July 07

16 July 07 : Mezzanine Floor Slab : Section 1

12 July 07 : Ground Floor : Spa Baths

11 July 07 : Ground Floor Slab : Section 8 : Part 2 of 4

10 July 07 : Ground Floor : Section 3 : Core Wall : Stairs

10 July 07 : Ground Floor Slab : Section 8 : Part 1 of 4

10 July 07 : Ground Floor : Section 2 : Core Wall : Lift & Stairs

Sunday 15 July 2007

Sat 14th July Football result : Comin 4 : 1 REE

Winners : Comin 5-a-side football team (top-left to bottom-left)

Mr. Trung – Coach – Foreman

Mr. Cuong – Forwards – Fire protection supervisor

Mr. Nghia – Goal keeper – Site Engineer

Mr. Ngoc – Forwards - Department Manager

Mr. Tuan – Defender - Elec Supervisor

Mr. Ha – Defender - Material Controller

Mr. Phuong – Middle - Elec Supervisor

Mr. Hai – Middle - Site Engineer

Mr. Bang – Middle - Chief Engineer

Monday 9 July 2007

06 July 07 to 09 July 07


09 July 07 : Ground Floor : 14 No. Columns

07 July 07 : Ground Floor Slab : Section 7

07 July 07 : Ground Floor : 7 No. Columns

06 July 07 : Ground Floor Slab : Section 6

02 July 07 to 05 July 07

Dung (AIC)

05 July 07 : Ground Floor : 10 No. Columns

04 July 07 : Ground Floor Slab : Section 6

03 July 07 : Ground Floor Slab : Section 5

02 July 07 : Ground Floor Slab : Section 4

Saturday 7 July 2007

Progress 31 May 07 to 30 June 07


Panoramic view of the site from the S.E. Corner : 30 June 07



Panoramic view of the site from the S.E. Corner : 31 May 07

Monday 2 July 2007

Ground Floor Slab : Section 4




Hoan (AIC) , Phu (REE)

Concrete placing to Ground Floor Section 4 will take place this evening

Sunday 1 July 2007

Ground Floor Slab : Section 2

Lei (BUCG) , Mr. Tu (BUCG) , Mr. Song (BUCG)

Concrete placing to Section 2 of the Ground Floor Slab was completed on Friday 29 June

Saturday 30 June 2007

Ground Floor Slab : Section 3


Hai jing (BUCG) , Andrew (AIC) , Tao (BUCG) , Wang (BUCG) , Cuong (AIC)

Heavy rain meant no significant site activity until 2:00pm. Concrete placing to Section 3 of the Ground Floor Slab will take place this evening.