East Tower
Floor 09 : Slab 50% completed
Floor 08 : Slab completed 21st November 07
Floor 07 : Slab completed 12th November 07
West Tower
Floor 08 : Slab 25% completed
Floor 07 : Slab completed 23rd November 07
Floor 06 : Slab completed 13th November 07
Sunday 2 December 2007
Sunday 4 November 2007
Progress Update : 05 November 07
East Tower :
Floor 07 : Under Construction
Floor 06 : Slab completed 01 November 07
Floor 05 : Slab completed 21 October 07
Floor 04 : Not used
Floor 03 : Slab completed 02 October 07
West Tower :
Floor 06 : Under construction
Floor 05 : Slab completed 02 November 07
Floor 04 : Not used
Floor 03 : Slab completed 20 October 07
View across West Lake from West Tower Floor 06
Panoramic view looking South : End October 07
Floor 07 : Under Construction
Floor 06 : Slab completed 01 November 07
Floor 05 : Slab completed 21 October 07
Floor 04 : Not used
Floor 03 : Slab completed 02 October 07
View across West Lake from East Tower Floor 07
West Tower :
Floor 06 : Under construction
Floor 05 : Slab completed 02 November 07
Floor 04 : Not used
Floor 03 : Slab completed 20 October 07
View across West Lake from West Tower Floor 06
Panoramic view looking South : End October 07
Sunday 23 September 2007
Floor 01 & Floor 02 : Structure : Completed
Sunday 19 August 2007
01 August 07 - 19 August 07
Until 25th August almost all workers are concentrating on completing the huge Transfer Beams on the 1st Floor.
Once Transfer Beams are completed ; vertical progress of the towers can recommence.
A small number of workers have been allocated to finish the swimming pool structure also by 25th August.
Maximum number of workers at site = 410
Once Transfer Beams are completed ; vertical progress of the towers can recommence.
A small number of workers have been allocated to finish the swimming pool structure also by 25th August.
Maximum number of workers at site = 410
Monday 6 August 2007
Friday 27 July 2007
22nd July 07 to 27 July 07
17th July 2007 to 21 July 2007
Wang Lin (BUCG) & Yang Shuli (BUCG)
21 July 07 : Mezzanine Floor Slab : Section 4
21 July 07 : Mezzanine Floor Slab : Section 3
17 July 07 : Mezzanine Floor : Section 1 : 6 No. Columns
17 July 07 : Mezzanine Floor Slab : Section 2
17 July 07 : Ground Floor Slab : Section 8 : Part 4 of 4
17 July 07 : Ground Floor Slab : Section 8 : Part 3 of 4
21 July 07 : Mezzanine Floor Slab : Section 4
21 July 07 : Mezzanine Floor Slab : Section 3
17 July 07 : Mezzanine Floor : Section 1 : 6 No. Columns
17 July 07 : Mezzanine Floor Slab : Section 2
17 July 07 : Ground Floor Slab : Section 8 : Part 4 of 4
17 July 07 : Ground Floor Slab : Section 8 : Part 3 of 4
Tuesday 17 July 2007
10th July 07 to 16th July 07
16 July 07 : Mezzanine Floor Slab : Section 1
12 July 07 : Ground Floor : Spa Baths
11 July 07 : Ground Floor Slab : Section 8 : Part 2 of 4
10 July 07 : Ground Floor : Section 3 : Core Wall : Stairs
10 July 07 : Ground Floor Slab : Section 8 : Part 1 of 4
10 July 07 : Ground Floor : Section 2 : Core Wall : Lift & Stairs
12 July 07 : Ground Floor : Spa Baths
11 July 07 : Ground Floor Slab : Section 8 : Part 2 of 4
10 July 07 : Ground Floor : Section 3 : Core Wall : Stairs
10 July 07 : Ground Floor Slab : Section 8 : Part 1 of 4
10 July 07 : Ground Floor : Section 2 : Core Wall : Lift & Stairs
Sunday 15 July 2007
Sat 14th July Football result : Comin 4 : 1 REE
Winners : Comin 5-a-side football team (top-left to bottom-left)
Mr. Trung – Coach – Foreman
Mr. Cuong – Forwards – Fire protection supervisor
Mr. Nghia – Goal keeper – Site Engineer
Mr. Ngoc – Forwards - Department Manager
Mr. Tuan – Defender - Elec Supervisor
Mr. Ha – Defender - Material Controller
Mr. Phuong – Middle - Elec Supervisor
Mr. Hai – Middle - Site Engineer
Mr. Bang – Middle - Chief Engineer
Monday 9 July 2007
06 July 07 to 09 July 07
02 July 07 to 05 July 07
Saturday 7 July 2007
Progress 31 May 07 to 30 June 07
Monday 2 July 2007
Sunday 1 July 2007
Ground Floor Slab : Section 2
Saturday 30 June 2007
Ground Floor Slab : Section 3