Floor 01 & Floor 02 : Structure : Completed
Floor 02 Structure was completed on 20th Sept 07
Swimming Pool Structure was completed on 16th Sept 07
Floor 01 Structure (including Transfer Beams ) was completed on 27th August 07
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
GOLDEN WESTLAKE EXECUTIVE RESIDENCES - HANOI - VIETNAM
CONSTRUCTION PROGRESS
OWNER :
HA VIET TUNG SHING CO. LTD.
www.tungshinggroup.com
PROJECT MANAGER :
AIC MANAGEMENT CO. LTD.
www.aicmanagement.net
MAIN CONTRACTOR :
BEIJING URBAN CONSTRUCTION INTERNATIONAL (BUCG) www.bucg-intl.com
MECHANICAL SUB-CONTRACTOR :
REE (REFRIGERATION & ELECTRICAL ENGINEERING CO. LTD.)
ELECTRICAL SUB-CONTRACTOR :
COMIN VIETNAM
Blog Archive
►
2008
(7)
►
August
(2)
►
May
(2)
►
March
(2)
►
January
(1)
▼
2007
(15)
►
December
(1)
►
November
(1)
▼
September
(1)
Floor 01 & Floor 02 : Structure : Completed
►
August
(2)
►
July
(9)
►
June
(1)
No comments:
Post a Comment