Wednesday 2 January 2008
Progress Update : 31st December 2007
View across West lake from West Tower Floor 12
West Tower
Floor 12 slab : under construction
Floor 11 slab completed : 30th Dec 07
Floor 10 slab completed : 22nd Dec 07
Floor 09 slab completed : 13th Dec 07
Floor 08 slab completed : 3rd Dec 07
East Tower
Floor 13 slab : under construction
Floor 12 slab completed : 31st Dec 07
Floor 11 slab completed : 22nd Dec 07
Floor 10 slab completed : 13th Dec 07
Floor 09 slab completed : 3rd Dec 07